Installation unitized curtain wall system.
Façade or curtain wall is a building envelope creates pleasure aesthetic to the building exterior.
It is offered in a wide range of options that can be customized to each project.
Ycu 750 tu unitized curtain wall system page 10 04 4013 00 effective date.
The curtain wall construction is classified as two as stick system and unitized system.
Curtain wall units are then hoisted up from the loading platform by means of this monorail and electric chain block and place in position at floor edge for fixing to the pre installed anchor brackets.
6 curtain wall installation guide curtain wall installation guide 7 1.
These are aluminium framed the non load bearing system which are hanging from the floor slabs and columns.
In this system most of the.
Long pieces of aluminum hence the name stick are inserted between floors vertically and horizontally between vertical members to support and transfer the load of the glass back to structure.
The vast majority of low to mid rise curtain walls are installed in this way.
Hence it is essential to keep in mind the mode of transportation and installation while planning the depth of facade.
General notes and guidelines f.
Individual installation of each component are not necessary as in sticky curtain wall system.
Since unitized curtain walls are the current state of the art in curtain wall technology designers consultants and contractors alike need to become familiar with these systems technical limitations so that we can develop effective designs that address their use for all areas of the building enclosure.
Stick system this is mostly adopted in low rise and mid rise buildings.
Kawneer s 2500 pg wall curtain wall system is a unitized solution engineered to meet these criteria and more.
Check the rough opening to ensure it matches drawing specifications.
To install fire insulation according to approved shop drawing at top part of concrete beam surface prior to curtain wall installation.
Whether you prefer stock length fabricated or pre assembled and pre glazed this is a unitized solution the way you want it.
Once the first mullion or corner piece is in place and plumb level fasten the bracket using either flathead or concrete screws depending on surface straight into the bracket holes.
April 22 2010 unit installation step 4 install l anchor note.
The size of the unitized curtain walls are dependent on the floor to floor height of the building.
All aluminum anchors and aluminum components of the curtainwall system must be separated from the structural steel and concrete with a nylon separator or material of similar compatibility.